Water and Sewer Corporation Reports Sixty-Per cent Projects Completion

MONROVIA, LIBERIA-Liberia Water and Sewer Corporation (LWSC) has reported sixty percent completion of a project earmarked under the government of Liberia’s one-hundred-day deliverable.

LWSC was tasked to ensure the cleaning of excess sewage spillage in Monrovia, restore water to central Monrovia, and improve water supply to Bushrod Island, Kakata, and Buchanan.

LWSC Managing Director Mohammed Ali told ELBC on Tuesday, 07 May 2024, that the reservoir, to restore water to central Monrovia was successfully repaired while the clearing of sewage is ongoing.

Mr. Ali said: “The entity could not complete its mandate under the government’s one hundred-day deliverables because it was tied to the National Budget which was not passed at the time”.

According to him, funds for the implementation of some of the projects undertaken by the LWSC were made available by donors, including the World Bank.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Hot this week

WASH Advocate Hails Pres. Boakai for Presidential Clean Cities Initiative

One of Liberia’s leading Water, Sanitation, and Hygiene (WASH)...

Pres. Boakai Recommits to Democratic Governance, Peace, Security

MONROVIA, LIBERIA-President Joseph Boakai has reiterated the Government of...

Labor Ministry Launches ‘Special Alien Permits Verification Exercise’

MONROVIA, LIBERIA-The Ministry of Labor has launched a ‘Special...

Edu. Minister Dr. Jallah Challenges 14 Agriculture Teachers to Study in Ghana

MONROVIA, LIBERIA-Education Minister, Dr. Jarso Jallah, has challenged fourteen...

Nat’l Commission on Arms Calls for Arms Registration Before April 2027

MONROVIA, LIBERIA-The Liberia National Commission on Arms is calling...

Related Articles

Popular Categories